Tuesday 13 October 2015

HC allowed sec. 80-IB relief for entire housing project though completion certificate wasn't granted

IT: Where assessee had completed construction of its entire housing project and applied for Building use permission/completion certificate within prescribed time-limit, it would be entitled to deduction under section 80-IB(10) notwithstanding fact that it could not receive permission for its entire project